Focusing on efficiency and ignoring effectiveness is the root cause of most software project failures.
Effectiveness is producing the intended or expected result. Efficiency is the ability to accomplish a job with a minimum expenditure of time and effort.
Effective software projects deliver code that the end users need; efficient projects deliver that code with a minimum number of resources and time.
Effectiveness is producing the intended or expected result. Efficiency is the ability to accomplish a job with a minimum expenditure of time and effort.
Effective software projects deliver code that the end users need; efficient projects deliver that code with a minimum number of resources and time.
Sometimes, we become so obsessed with things we can measure, i.e. project end date, kLOC, that we somehow forget what we were building
in the first place. When you're up to your hips in alligators, it's hard to remember you were there to drain the swamp.
Efficiency only matters if you are being effective.
After 50 years, the top three end-user complaints about software are:
- It took too long
- It cost too much
- It doesn't do what we need
Salaries are the biggest cost of most software projects, hence if it takes too long then it will cost too much, so we can reduce the complaints to:
The first issue is a complaint about our efficiency and the second is a complaint about our effectiveness. Let's make sure that we have common definitions of these two issues before continuing to look at the interplay between efficiency and effectiveness.
Are We There Yet?
Are you late if you miss the project end date?
That depends on your point of view; consider a well specified project (i.e. good requirements) with a good work breakdown structure that is estimated by competent architects to take a competent team of 10 developers at least 15 months to build. Let's consider 5 scenarios where this is true except as stated below:
Under which circumstances is the project late?
A. Senior management gives the team 6 months to build the software.
B. Senior management assigns a team of 5 competent developers instead of 10.
C. Senior management assigns a team of 10 untrained developers
D. You have the correct team, but, each developer needs to spend 20-35% of their time maintaining code on another legacy system
E. The project is staffed as expected
Here are the above scenarios in a table:
#
|
Team
|
Resource
Commitment
|
Months Given
|
Result
|
A
|
10 competent developers
|
100%
|
6
|
Unrealistic estimate
|
B
|
5
competent developers
|
100%
|
15
|
Under staffed
|
C
|
10 untrained developers
|
100%
|
15
|
Untrained staff
|
D
|
10 competent developers
|
65-80%
|
15
|
Team under committed
|
E
|
10 competent developers
|
100%
|
15
|
Late
|
Only the last project (E) is late because the estimation of the end date was consistent with the project resources available.
Other well known variations which are not late when the end date is missed:
- Project end date is a SWAG or management declared
- Project has poor requirements
- You tell the end-user 10 months when the estimate is 15 months.
If any of the conditions of project E are missing then you have a problem in estimation. You may still be late, but not based on the project end date computed with bad assumptions.
Of course, being late may be acceptable if you deliver a subset of the expected system.
It Doesn't Work
“It doesn't do what we need” is a failure to deliver what the end user needs. How so we figure out what the end user needs?
The requirements for a system come from a variety of sources:
- End-users
- Sales and marketing (includes competitors)
- Product management
- Engineering
These initial requirements will rarely be consistent with each other. In fact, each of these constituents will have a different impression of the
requirements. Y
You would expect the raw requirements to be contradictory in places. The beliefs are like the 4 circles to the left, and the intersection of their beliefs would be the black area.
You would expect the raw requirements to be contradictory in places. The beliefs are like the 4 circles to the left, and the intersection of their beliefs would be the black area.
- Everyone has a different point of view
- Everyone has a different set of beliefs about what is being built
- Everyone has a different capability of articulating their needs
- Product managers have varying abilities to synthesize consistent requirements
It is the job of product management to synthesize the different viewpoints into a single set of consistent requirements. If engineering starts before
requirements are consistent then you will end up with many fire-fighting meetings and lose time.
Many projects start before the requirements are consistent enough. We hope the initial requirements are a subset of what is required.
In practice, we have missed requirements and included requirements that are not needed (see bottom of post, data from Capers Jones)
The yellow circle represents what we have captured, the black circle represents the real requirements.
The yellow circle represents what we have captured, the black circle represents the real requirements.
We rarely have consistent requirements when we start a project, that is why there are different forms of the following cartoon lying around on the Internet.
If you don't do all the following:
- Interview all stakeholders for requirements
- Get end-users to articulate their real needs by product management
- Synthesize consistent requirements
Effectiveness vs. Efficiency
So, let's repeat our user complaints:
- It took too long
- It doesn't do what we need
It's possible to deliver the correct software late.
It's impossible to deliver on-time if the software doesn't work
Focusing on effectiveness is more important than efficiency if a software project is to be delivered successfully.
Ineffectiveness Comes from Poor Requirements
Most organizations don’t test the validity or completeness of their requirements before starting a software project.
The requirements get translated into a project plan and then the project manager will attempt to execute the project plan. The project plan becomes the bible and everyone marches to it. As long as tasks are completed on time everyone assumes that you are effective, i.e. doing the right
thing.
That is until virtually all the tasks are jammed at 95% complete and the project is nowhere near completion.
That is until virtually all the tasks are jammed at 95% complete and the project is nowhere near completion.
At some point someone will notice something and say, “I don’t think this feature should work this way”. This will provoke discussions between
developers, QA, and product management on correct program behavior. This will spark a series of fire-fighting meetings to resolve the inconsistency, issue a defect, and fix the problem. All of the extra meetings will start causing tasks on the project plan to slip.
We discussed the root causes of fire-fighting in a previous blog entry.
When fire-fighting starts productivity will grind to a halt. Developers will lose productivity because they will end up being pulled into the endless meetings. At this point the schedule starts slipping and we become focused on the project plan and deadline. Scope gets reduced to help make the project deadline; unfortunately, we tend to throw effectiveness out the window at this point.
With any luck the project and product manager can find a way to reduce scope enough to declare victory after missing the original deadline.
We discussed the root causes of fire-fighting in a previous blog entry.
When fire-fighting starts productivity will grind to a halt. Developers will lose productivity because they will end up being pulled into the endless meetings. At this point the schedule starts slipping and we become focused on the project plan and deadline. Scope gets reduced to help make the project deadline; unfortunately, we tend to throw effectiveness out the window at this point.
With any luck the project and product manager can find a way to reduce scope enough to declare victory after missing the original deadline.
The interesting thing here is that the project failed before it started. The real cause of the failure would be the inconsistent requirements.
But, in the chaos of fire-fighting and endless meetings, no one will remember that the requirements were the root cause of the problem.
What is the cost of poor requirements? Fortunately, WWMCCS has an answer. As a military organization they must tracks everything in a detailed fashion and perform root cause analysis for each defect (diagram).
This drawing shows what we know to be true.
The longer a requirement problem takes to discover, the harder and more expensive it is to fix!
A requirement that would take 1 hour to fix will take 900 hours to fix if it slips to system testing.
Conclusion
It is much more important to focus on effectiveness during a project than efficiency. When it becomes clear that you will not make the project end
date, you need to stay focused on building the correct software.
Are you tired of the cycle of:
- Collecting inconsistent requirements?
- Building a project plan based on the inconsistent requirements?
- Estimating projects and having senior management disbelieve it?
- Focusing on the project end date and not on end user needs?
- Fire-fighting over inconsistent requirements?
- Losing developer productivity from endless meetings?
- Not only miss the end date but also not deliver what the end-users need?
The fact that organizations go through this cycle over and over while expecting successful projects is insanity – real world Dilbert cartoons.
How many times are you going to rinse and repeat this process until you try something different? If you want to break this cycle, then
you need to start collecting consistent requirements.
Think about the impact to your career of the following scenarios:
- You miss the deadline but build a subset of what the end-user needs
- You miss the deadline and don't have what the end-user needs
You can at least declare some kind of victory in scenario 1 and your resume will not take a big hit. It's pretty hard to make up for scenario 2 no
matter how you slice it.
Alternatively, you can save yourself wasted time by making sure the requirements are consistent before you start development. Inconsistent requirements
will lead to fire-fighting later in the project.
As a developer, when you are handed the requirements the team should make a point of looking for inconsistent requirements. The entire team should go
through the requirements and look for inconsistencies and force product management to fix them before you start developing.
It may sound like a waste of time but it will push the problem of poor requirements back into product management and save you from being in endless meetings.
Cultivating patience on holding out for good requirements will lower your blood pressure and help you to sleep at night. Of course, once you get good requirements then you should hold out for proper project estimates :-)
<
Want to see another sacred cow get killed? Check out
Courtesy of Capers Jones via LinkedIn on 6/22It may sound like a waste of time but it will push the problem of poor requirements back into product management and save you from being in endless meetings.
Cultivating patience on holding out for good requirements will lower your blood pressure and help you to sleep at night. Of course, once you get good requirements then you should hold out for proper project estimates :-)
<
Moo? |
Want to see another sacred cow get killed? Check out
Customers themselves are often not sure of their requirements.
For a large system of about 10,000 function points, here is what might be seen for the requirements.
This is from a paper on requirements problems - send an email to capers.jones3@gmail.com if you want a copy.
Requirements specification pages = 2,500
Requirements words = 1,125,000
Requirements diagrams = 300
Specific user requirements = 7,407
Missing requirements = 1,050
Incorrect requirements = 875
Superfluous requirements = 375
Toxic harmful requirements = 18
Initial requirements completeness = < 60%
Total requirements creep = 2,687 function points
Deferred requirements to meet schedule = 1,522
Complete and accurate requirements are possible < 1000 function points. Above that errors and missing requirements are endemic.
I like what you are saying, but one can tackle effectiveness with iterations and a tight control of how the project grows. If the project is waterfall, then that option doesn't exist, which is why many of us (even if we aren't purely Agile) have switched the way we build.
ReplyDeleteEffectiveness generally comes into play with the leadership, they need to make sure that the right direction is set and the right information is gathered. Efficiency on the other hand affects everyone on the team. Programmers can go rogue and start focusing on things that they think are important, but aren't going to help the project as a whole.
For me, it's still more importance to focus on efficiency, mostly because it has often been the worst problem but also because it is a manageable problem completely within the scope of the team. Fixing a bad requirements stream usually means tackling some difficult external issues.
If you make the date, but need to tweek it a bit for the next release, they'll generally forgive you. If it is the best system ever, but it is two years too late ...
Paul.
I like your discussion but all of this is academic, at the end of the day, one can argue efficiency over effectiveness or where defect fixes need to be picked up, but I.T. software development is not an exact science. Users generally don't fully understand whether their needs are met, until they see something in front of them (some of the benefits of the new buzz word Agile). In defect management the Rashomon effect plays havoc with timelines and costs…, let me give you some simple advice … just manage it !
ReplyDeleteThe truth is, we tend to forget something far more fundamental…, everything has a price everything started off with a justification. You always justify the cost of the estimate with what it will save you over time, simple basic business case. The truth is, at what point do the economics no longer justify the outcome ? t doesn't matter whether you debate efficiency over effectiveness or whatever other justification we place on a missed deliverable. It all boils down to achieving the end game and ensuring the customers business case (true or otherwise) is kept as intact as possible.
Perception of missed deliverables can be attributed to a plethora of issues, all valid or reasonable or avoidable. The true genius is getting to that end date with the least change in cost and time, resolving the obstacles, effectively communicating the results and above all ensuring the whole team (including business) has the same focus, same outcome same drive to the end point.
The I.T. landscape is scattered with bodies of effective and efficient losers…, but at the end of the day, only those worthy enough to have achieved the impossible can claim victory!
I claim efficiency is not for losers, but losers are inefficient! and comments are not for losers, but losers don't comment to show how efficient they are in effectively screwing up support of any code they write….
For me the real title should be " Winning is NOT for losers ! "
I believe efficiency and affordability are key to project delivery. It is clear that balancing these two opposites is difficult ! Most times, efficient people are not cheap, and so your affordability ratio / head is normally higher…, having said this, yet it is an art to complete the project, I believe the article clearly shows the areas that one should focus on, and shows the underlying misnomers that even the best fall into!
Delete